Finding · F-IAQ2-P2P-01
Purchase orders released above delegated threshold
ClosedP2P-01 · Purchase orders follow approval thresholds; no self-approvalProcure-to-PayQ2 2026 Unified Program Review
Fraud indicator
Rating
No
High
Medium
Low
Requirement to validation
Requirement
ISO-A.5.3 · ITGC-BP-01 · ITGC-SOD-01 · SOC2-CC5.2
mapped
Policy
Payments Security Policy
pol-payments
Control
P2P-01
Purchase orders follow approval thresholds; no self-approval
Application
SAP S/4HANA
mapped
Evidence · Q3
2 items
2 approved · 0 pending · 0 rejected
Test · Q3
Fail
TST-ITGC-P2P-01 · Medium confidence
Finding
F-IAQ2-P2P-01 · High
Closed
Action
Priya Sharma
REM-F-IAQ2-P2P-01 · Closed
Validation
Failed
as recorded
Observation
Raised 2026-06-20 in the Q2 2026 internal audit baseline. 2 of 40 sampled purchase orders above INR 5 lakh were released by department heads instead of the Financial Controller.
Applications: SAP S/4HANA.
Potential risk
Unauthorised or erroneous transactions could go undetected and expose Meridian to financial loss and regulatory action.
Root cause
SAP release strategy did not enforce the revised delegation-of-authority bands.
Agreed action plan
Remediate: purchase orders released above delegated threshold.
Management response: Management agreed and committed to remediate before the Q3 review.
- Action
- REM-F-IAQ2-P2P-01
- Owner (FPR)
- Priya Sharma
- Target date
- 31 Jul 2026
- Priority
- High
- Status
- Closed
- Validation
- Failed · planned 26 Sep 2026
Evidence for this control (3)
| Evidence | Title | Control | Source system | Collected | Status |
|---|---|---|---|---|---|
| ITGC-REQ-017 | SAP S/4HANA: No self-approved purchase orders | P2P-01 | SAP S/4HANA | 9 Oct 2026 | Accepted |
| ITGC-REQ-018 | SAP S/4HANA: Release strategy matches threshold | P2P-01 | SAP S/4HANA | 8 Oct 2026 | Accepted |
| Q2-EV-014 | SAP S/4HANA · ticket sample (Q2) | P2P-01 | SAP S/4HANA | 25 Jun 2026 | Rejected |
Tests of this control (2)
| Test | Control | Cycle | Tested | By | Result | Confidence |
|---|---|---|---|---|---|---|
| TST-ITGC-P2P-01 | P2P-01 · Purchase orders follow approval thresholds; no self-approval | Q3 2026 Unified Program Review | 6 Oct 2026 | Vikram Mehta, Farah Khan · Meridian Internal Audit | Fail | Medium |
| TST-Q2-P2P-01 | P2P-01 · Purchase orders follow approval thresholds; no self-approval | Q2 2026 Unified Program Review | 18 Jun 2026 | Farah Khan, Vikram Mehta · Meridian Internal Audit | Fail | High |